Ferrowind Partners

Primary metals · 2025

Foundry throughput recovery

A fictional foundry case study: recovering casting-line capacity by fixing changeover and scrap, without a new furnace.

Client
Brackenhill Metals
Published

Before and after

Before and after
Before and afterBeforeAfter
Overall equipment effectiveness61%78%
Scrap rate8.4%3.1%
Changeover time42 min18 min

Context

Brackenhill Metals (fictional) runs a 140,000 tonne-per-year foundry with three casting lines. OEE had drifted to 61%, scrap was above 8%, and the team was preparing a capital request for a fourth furnace.

The plant manager suspected the furnace was the constraint. The production data suggested something else: the line lost more time between casts than during them.

Approach

A two-week diagnostic combined time studies, changeover video, and a scrap Pareto by alloy and shift.

  • 38% of changeover delay was waiting for tooling and pre-heat checks that could run in parallel.
  • Two alloy grades accounted for 61% of scrap, both linked to a missing pre-cast temperature check.
  • The schedule grouped grades in a way that forced unnecessary cleanouts.

We moved pre-heat to a parallel station, built an external setup checklist, and changed the scheduling rule to group compatible grades. No furnace was ordered.

Results

  • OEE moved from 61% to 78% over four months.
  • Scrap fell from 8.4% to 3.1%.
  • Changeover dropped from 42 minutes to 18 minutes.

The capital request was withdrawn. The plant instead spent roughly $180,000 (fictional) on fixtures, a pre-heat station, and operator training.

What changed

The durable change was a ten-minute daily line review with one metric: minutes lost between casts. Six months later, the plant still runs the same checklist and schedule rule.

Fictional case study for portfolio purposes. Client names, sites, and results are invented.

Case studies

Have a constraint like this?

Bring the line and the metric. We will start with a short diagnostic.