Ferrowind Partners

Building materials · 2025

Cement plant energy program

A fictional cement case study: reducing energy per tonne with metering, idle-load removal, and a sequenced heat-recovery project.

Client
Calder Cement Works
Published

Before and after

Before and after
Before and afterBeforeAfter
Energy per tonneBaseline-11%
CO2e avoided09,400 t/yr
Program paybackUnknown2.6 years

Context

Calder Cement Works (fictional) faced rising energy costs and a board request for an emissions plan. The plant had monthly utility bills and no line-level metering, so every discussion about savings ended in the same argument about the kiln.

The team assumed the only meaningful lever was a major kiln upgrade. The data had not been collected to prove or disprove it.

Approach

We ran a six-week metering campaign across the kiln, raw mill, cement mill, and compressed-air system, then built a load profile by shift.

  • 17% of compressed-air load occurred during periods with no production demand.
  • Cooler exhaust held enough recoverable heat to preheat raw-mill feed.
  • Two large motors idled for more than 40% of scheduled hours.

The program sequenced no-cost operational fixes first, then a heat-recovery project with a measured baseline.

Results

  • Energy per tonne fell 11% across the metered areas.
  • The site avoided roughly 9,400 tonnes of CO2e per year (fictional).
  • The combined program payback was 2.6 years, with the operational fixes paying back in under four months.

What changed

The plant now reviews a shift-level energy dashboard in the daily production meeting. The heat-recovery project was approved on its own numbers, not on a vendor estimate.

Fictional case study for portfolio purposes. Client names, sites, and results are invented.

Case studies

Have a constraint like this?

Bring the line and the metric. We will start with a short diagnostic.